The remodeling of the 6445 building is slightly ahead of schedule. The vestibule addition has been added, interior metal stud framing is nearly complete and exterior concrete sidewalks have been poured. Fire sprinkler, mechanical, plumbing and electrical rough-ins are complete. Masons are doing the brick work around the window openings, and preparations for window installation are going smoothly. The building should be enclosed before the October Board meeting.
Two separate ad hoc groups are working on programming the building. One group is programming the workroom, kitchen, storage and support areas, and the other group is programming the HR/Business office staff areas. If you have any concerns or questions regarding the programming of the workroom, kitchen, storage or support areas, please contact Terri Barnes in the Johnston office at ext. 14310 or at tbarnes@aea11.k12.ia.us.