Construction Elements
- Steel studs are in place and the ceiling framing with steel studs is done.
- Concrete curbs and sidewalks have been poured.
- Brick layers will be finished shortly.
- Phone line conduit has been installed.
- The plumbers are working on rough-ins.
- Pigott has measured for walls.
- Six geothermal wells still need to be drilled. (There will be around 30 wells when we are done.)
- Heat pumps will be delivered the last week of September.
- Ducts will be started soon, although many ducts will wait for heat pumps.
- Geo-piping is in progress.
- The transformer pad has been poured.